Ekurhuleni’s multi-billion rand housing project stalls as nearby shack dwellers demand services
“The government has surely forgotten us” says Daggafontein pensioner
- About 2,000 people living at three settlements near the City of Ekurhuleni’s multi-billion rand Daggafontein Mega City Housing project say they want the homes and services they were promised.
- The housing project was initially launched in 2016, but construction at the site started in 2017. The project has since stalled due to issues with the previous contractor. The City says it expects to complete the project over a ten year period.
- Now residents at the three informal settlements say they are still waiting for confirmation that they will be housed once houses are built at the mega city project.
- They also want the municipality to improve their basic services immediately.
The City of Ekurhuleni’s multi-billion rand Daggafontein Mega Housing project was expected to be a flagship for affordable housing in the city. It was set to provide about 18,000 homes.
The development site was initially launched in 2016, but construction at the site began in 2017. The cost for the development is expected to be well over the initial estimated R10-billion budget. The project had stalled due to lockdown in 2020 and resumed in 2021 until the previous contractor’s contract lapsed in December 2022. The City has now mandated itself to complete the project over a ten year period.
Now, more than five years after the project was launched, the building site appears to be far from complete, with only sewerage piping and tarred roads with no houses or signage at the site.
A few hundred metres from the new mega development site are three informal settlements, namely Daggafontein, Kwasa Village and Anchor/N1.
About 2,000 people live in the three settlements, according to community leaders. The residents say they have been waiting to hear if they qualify to be beneficiaries once houses are built at the mega city project. According to residents, the first phase of the housing project was expected to be completed by the end of 2019.
Residents from the informal settlements protested in May 2022 to demand that they be given water, toilets and for electricity to be installed in their shacks. GroundUp has seen a letter, handed out to shack dwellers by an official from the infrastructure portfolio of Ward 76 in June 2022, stating that they are to benefit from the Daggafontein housing project.
The City then also conducted a census of the settlements in July 2022 to determine how many households needed services like water and toilets. To date no additional services have been offered and the City has been mum on the mega housing project, say residents.
At Daggafontein informal settlement, up to ten families share one chemical toilet. There are a few communal taps but residents say they were told that the City could only offer limited services because they are on privately owned land.
Sisikazi Madhobe, 73, said she has been waiting for a house for decades. She said that some neighbours help her fetch water from a tap a few metres from her shack.
She said she spends most of her pension money on repairing her leaking roof each winter. Madhobe said as the mega city project launched, officials from the City came to speak to them about the project. She said she and other elderly residents were given a verbal promise of houses in the new development.
“I want the government to build me a house. I have sleepless nights worrying about whether l will ever get a house in this life. The government has surely forgotten us.” she said.
The Kwasa Village settlement is on land belonging to an independent primary school. While the settlement has over 500 shacks, some families live in abandoned mineworker houses.
Penelope Nomaswazi said she moved here with her husband in 2001 and paid rent for the old mine worker home to the previous landowner. She said since the old owners left, they haven’t had electricity or water. The toilet in the house does not work, so she has to use the communal chemical toilet shared with ten other families in the informal settlement.
Nomaswazi said she was also promised a home in Mega City.
Reverend Sharron Anne Dinnie of the Anglican Church, who owns the Kwasa land and primary school, said she acquired the 20-hectares from the previous owner, John Borat.
“Our vision is to provide good education for vulnerable children. The municipality promised that it would move the occupiers to Mega City by now. The fact that this has not happened is standing in the way of the future of vulnerable children who deserve quality education.
“I have sent emails to the municipality informing them of our intentions to build a High School but received no answers,” said Dinnie.
The N17 informal settlement is situated on an old farm next to the N17 freeway. Residents here complain that more than five families share one toilet, their shacks have no electricity and there are not enough taps. The area also has large old trees which have fallen and damaged some shacks.
Letty Mnguni, chairperson of the N17 housing committee, said when the farm owner died in 1994, the informal settlement mushroomed.
City of Ekurhuleni spokesman Zweli Dlamini confirmed that the occupiers from all three settlements are living on private land. “It would not make sense to provide permanent services to temporary settlements on privately owned land,” he said.
Asked why the Mega City housing project has stalled, Dlamini only said that the City was busy appointing a new contractor. “The contract given to TCT Civils and Construction lapsed in December 2022,” he said.
According to Dlamini the previous contractors had only completed roads, stormwater, water and sewer provision.
However, residents say at a public meeting in 2021 they were promised 900 units by end of December 2022, which never materialised. Dlamini said the City has now mandated itself to complete the project over a ten-year period.
Dlamini said the budget allocations for the project was as follows: R118 million in 2019, R62 million in 2020, R36 million in 2021 and R35 million in 2022. Dlamini did not respond to questions about how much the City had already paid to the previous contractors and how much would be allocated for the remainder of the project.
Next: “People put borders in their hearts, that’s where xenophobia comes from”
Previous: R26-million Lehae Library opens seven years after construction started
© 2023 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.
You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.
We put an invisible pixel in the article so that we can count traffic to republishers. All analytics tools are solely on our servers. We do not give our logs to any third party. Logs are deleted after two weeks. We do not use any IP address identifying information except to count regional traffic. We are solely interested in counting hits, not tracking users. If you republish, please do not delete the invisible pixel.